Problem: Complete report PMR and WBI September 2026
Action:
Do complete data check sheet PMR analyzer L63 2K1-L63 2K2-L63 2K3-483 2K1-463 2K1-443 2K1-423 2K1; PMR Temperature  IR TAD-T scanner-CCTV-Camera burner month august-september 2026 ( JAJAT & ADI )

Status: done